Embodiment Construction
[0077] Such as Figure 1-2 As shown, the anti-leakage construction method of the anchor cable in the deep foundation pit support project includes the construction technology of the anti-leakage auxiliary pile of the anchor cable and the construction technology of the plugging of the end of the anchor cable lock;
[0078] Wherein, described anchor cable anti-seepage auxiliary pile construction technology comprises the following steps:
[0079] 1) Measuring and setting out
[0080] According to the pile position line determined by the plan, use small wooden piles or other obvious materials to measure and place specific pile points, and number them as the original data of construction records to locate and correct verticality:
[0081] 2) Pile driver in place and centered
[0082] When the drilling rig is placed and positioned, the machine base should be flat and the machine tower vertical before drilling. The vertical deviation of the mixing pile should not exceed 1.5%, and th...