Soft geological foundation pit excavation construction method for existing line station
A construction method and technology for existing lines, applied in excavation, infrastructure engineering, artificial islands, etc., can solve the problems of existing line station structure safety, new line soft soil foundation pit construction, difficult construction, low construction efficiency, etc., to achieve Automatic monitoring effect is good, construction efficiency is improved, and safety is high
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0059] See attached figure 1 as shown, figure 1 It is a flow chart of a method for excavating foundation pits in soft ground for existing railway stations provided by the present invention. The invention provides a construction method for excavating foundation pits in soft ground for existing railway stations. The method includes steps: S1, construction preparation.
[0060] Specifically, before construction, it is necessary to prepare the work arrangement for the excavation of the foundation pit, the deployment of construction personnel, etc. The technician confirms the construction drawings, and when the confirmation is correct, it is handed over to the construction personnel, who will operate it, thereby improving the excavation efficiency of the foundation pit.
[0061] S2. Monitoring the foundation pit to be excavated.
[0062] Specifically, before the excavation of the foundation pit, by arranging monitoring points for the foundation pit and the operating station, by ...