High-efficiency conversion device for non-fluctuation stove changing of hot blast stoves and control method
A conversion device and hot blast furnace technology, applied in furnaces, blast furnaces, heating furnaces, etc., can solve problems such as fluctuations and long charging time, and achieve the effect of reducing furnace replacement time and improving work efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0038] A high-efficiency conversion device for non-fluctuating furnace change of a hot blast furnace of the present invention includes a blower 1 and an air compressor 2, the air compressor 2 is connected with the intake valve of the gas storage tank 3, and the exhaust port of the gas storage tank 3 passes through the pressure reducing valve. 4 is communicated with the charging pipeline, the charging pipeline is connected with the charging valve 13 of each hot blast stove 5, the bottom of each hot blast stove 5 is provided with a first cold air valve 7, and the first cold air valve 7 is connected with the blower 1 through the cold air main pipe There is a differential pressure gauge 8 between the cold air main pipe and the charging pipe, a flow meter is provided in the charging pipe at the rear end of the pressure reducing valve 4; the air storage tank 3 is provided with a safety valve 9.
[0039] When in use, the air compressor 2 compresses the air and sends the compressed air i...
Embodiment 2
[0041] The inventor found that adding a set of air compressors and a gas supply station alone through the above solution requires a lot of land and a lot of money, which increases the burden and risk for the enterprise to build a factory. Further improvements.
[0042] A high-efficiency conversion device for non-fluctuating furnace change of a hot blast stove 5 of the present invention includes a blower 1, and the air outlet of the blower 1 is connected with the first cold air main pipe and the second cold air main pipe at the same time, and the connection port of the first cold air main pipe and the blower 1 There is a pressure equalizing valve 10; an air pressure sensor 11 is provided at the connection port of the second cold air main pipe and the blower 1, and the second cold air main pipe at the rear end of the air pressure sensor 11 is provided with a second cold air main pipe intake valve, and the first cold air main pipe passes through the first cold air main pipe. A co...