[0035] Attached to the following Figure 1-3 This application will be described in further detail.
[0036] The embodiment of the present application discloses a construction method for grouting reinforcement of hollow slabs of old concrete pavement. Include the following steps:
[0037] S1. Empty plate detection. Specifically, according to the requirements of the construction drawings, the construction personnel use the Beckman beam pavement deflection instrument to test the deflection value of the entire line panel, set the deflection value to L, and record the L value of each measuring point, so as to detect one by one. Empty plate, mark the drilling position on each empty plate.
[0038] S2, grouting hole construction. specifically:
[0039] S21, using a drilling rig to drill a grouting hole according to the marked drilling position. When the marked position is near the corner of the hollow plate, drill a grouting hole 50cm away from the edge of the hollow plate. Th...
PUM