Horizontal backfill grouting construction process of pressure conduit for hydraulic power plant
A construction technology and pressure pipeline technology, which is applied in the field of horizontal backfill grouting construction technology for pressure pipelines in hydropower stations, can solve the problems of large pipeline diameter, high pressure and affecting the quality of steel pipes.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0014] The present invention will be described in more detail below in conjunction with the accompanying drawings and embodiments.
[0015] refer to figure 1 , arrange 8 grouting pipelines within a grouting section of 41.6m and 80cm of the inner roof arch, cut and number the main pipes on site according to the buried length, and open holes according to the position of the branch pipes in the grouting section controlled by each numbered pipeline. The hole diameter is Φ20mm. Among them, 1~3, 5~7 are main grouting pipes, 4, 8 are auxiliary grouting pipes and exhaust pipes. A branch pipe is arranged every 1.4m on the control section of the main grouting pipe, and a branch pipe is arranged every 2.0m on the auxiliary pipe. The branch pipe outlet of the main grouting pipeline and the branch pipe outlet of the auxiliary pipeline are 3-5cm and 2cm away from the concrete spray protection surface respectively. Among them, the main pipe and the exhaust pipe are all galvanized iron pip...