Method and device for jointing reinforcement and vibration readjustment construction of pre-embedded bolt

A technology of pre-embedded bolts and construction methods, applied in basic structure engineering, construction, building construction, etc., can solve the problems of unrecoverable steel, large deviation, large waste, etc., to reduce construction costs, improve installation accuracy and engineering. quality, the effect of reducing steel consumption and waste

Active Publication Date: 2009-09-23
中国冶金科工股份有限公司
View PDF0 Cites 7 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] At present, the construction method of pre-embedded bolts in concrete foundation is welding and fixing method. The support is fixed by section steel or steel bars in the foundation body, and the pre-embedded bolts are first welded and fixed together with the foundation steel bars and formwork supports, and then concrete is poured and formed at one time; this method exists Two major defects: first, each pre-embedded bolt must first be provided with an unshaped steel fixing frame inside and outside the foundation, and the steel cannot be recycled, resulting in a large amount of waste; The deviation is large, which affects the installation accuracy and engineering quality of embedded bolts

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method and device for jointing reinforcement and vibration readjustment construction of pre-embedded bolt
  • Method and device for jointing reinforcement and vibration readjustment construction of pre-embedded bolt

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0031] In a construction project, this method and device were used for the installation of foundation embedded bolts. A total of 1,200 embedded bolts were installed, and the installation accuracy was 1,200 qualified at one time, with a one-time pass rate of 100%. And the praise of the owner.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a method and a device for jointing reinforcement and vibration readjustment construction of a pre-embedded bolt, belonging to a civil engineering construction method. The method is characterized in that a fixed frame is installed outside a concrete foundation; the fixed frame is provided with a tuner and a crossed buckle; are connected with the pre-embedded bolt is extended by a jointing rod and a jointing sleeve in a spurious way; the tuner and the crossed buckle suspends the pre-embedded bolt in place and the foundation concrete is grouted; the exact positioning of the pre-embedded bolt is realized by the tuner and the vibration of the concrete, thus ensuring the installation precision of the pre-embedded bolt; and the method comprises the construction steps of 1 installing the fixed frame; 2. installing the jointing rod, the jointing sleeve, the tuner and the pre-embedded bolt; 3. aligning and adjusting the pre-embedded bolt primarily; 4. grouting the foundation concrete; and 5. aligning and adjusting the pre-embedded bolt secondarily. The device is safe and reliable for use, reduces the consumption and waste of the steel material, reduces the construction cost, and improves the installation precision and engineering quality of the pre-embedded bolt.

Description

technical field [0001] The invention belongs to a civil construction method, in particular to a construction method of pre-embedded bolts. Background technique [0002] At present, the construction method of pre-embedded bolts in concrete foundation is welding and fixing method. The support is fixed by section steel or steel bars in the foundation body, and the pre-embedded bolts are first welded and fixed together with the foundation steel bars and formwork supports, and then concrete is poured and formed at one time; this method exists Two major defects: first, each pre-embedded bolt must first be provided with an unshaped steel fixing frame inside and outside the foundation, and the steel cannot be recycled, resulting in a large amount of waste; The deviation is large, which affects the installation accuracy and engineering quality of the embedded bolts. Contents of the invention [0003] The purpose of the present invention is to propose a construction method and devi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E02D15/02E04B1/41
Inventor 尹万云晏维平刘守城
Owner 中国冶金科工股份有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products