Production method of concrete pipe pile
A technology for a concrete pipe pile and a production method, which is applied in the directions of reinforcement molding, ceramic molding machines, manufacturing tools, etc., can solve problems such as wasting manpower, and achieve the effect of reducing production costs.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0028] The production method of concrete pipe pile of the present invention comprises the following steps:
[0029] A. After loading the cage bars required for the production of pipe piles into the mould, close the upper and lower moulds, and tighten the screws;
[0030] B. Transport the pre-prepared concrete material to the inner cavity of the mold;
[0031] C. Use a tensioning machine to stretch the cage bars in the above-mentioned mold, and apply prestress to the mold; the specific operation is to fix the cage bars at the head end of the pipe mold on the tensioning machine with anchors, and turn on the tensioning machine. The specification and the reinforcement number of production pile, regulate tension strength, and general tension strength is 0.5-0.8 times of cage reinforcement total strength, adopts 0.7 times of cage reinforcement total strength as tension strength to cage reinforcement stretching in the present embodiment 10-60 seconds;
[0032] D. Hang the mold on t...
Embodiment 2
[0034] The production method of concrete pipe pile of the present invention comprises the following steps:
[0035] A. After loading the cage bars required for the production of pipe piles into the mould, close the upper and lower moulds, and tighten the screws;
[0036] B. Transport the pre-prepared concrete material to the inner cavity of the mold;
[0037] C. Use a tensioning machine to stretch the cage bars in the above-mentioned mold, and apply prestress to the mold; the specific operation is to fix the cage bars at the head end of the pipe mold on the tensioning machine with anchors, and turn on the tensioning machine. The specification and the reinforcement number of production pile, regulate tension strength, and general tension strength is 0.5-0.8 times of cage reinforcement total strength, adopts 0.5 times of cage reinforcement total strength as tension strength to cage reinforcement stretching in the present embodiment 60 seconds;
[0038] D. Hang the mold on the ...
Embodiment 3
[0040] The production method of concrete pipe pile of the present invention comprises the following steps:
[0041] A. After loading the cage bars required for the production of pipe piles into the mould, close the upper and lower moulds, and tighten the screws;
[0042] B. Transport the pre-prepared concrete material to the inner cavity of the mold;
[0043] C. Use a tensioning machine to stretch the cage bars in the above-mentioned mold, and apply prestress to the mold; the specific operation is to fix the cage bars at the head end of the pipe mold on the tensioning machine with anchors, and turn on the tensioning machine. The specification and the reinforcement number of production pile, regulate tension strength, and general tension strength is 0.5-0.8 times of cage reinforcement total strength, adopts 0.8 times of cage reinforcement total strength as tension strength to cage reinforcement stretching in the present embodiment 10 seconds;
[0044] D. Hang the mold on the ...
PUM

Abstract
Description
Claims
Application Information

- R&D
- Intellectual Property
- Life Sciences
- Materials
- Tech Scout
- Unparalleled Data Quality
- Higher Quality Content
- 60% Fewer Hallucinations
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2025 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com