Method for removing zinc from zinc hydrometallurgy acidic leaching residue flotation silver concentrate
A technology of acid leaching and hydrometallurgy zinc, applied in the direction of improving process efficiency, can solve the problems of waste of resources and low recovery rate of zinc
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
preparation example Construction
[0019] A, the preparation of leaching solution, add water in the leaching tank, then start the mixer to stir and add sulfuric acid slowly, prepare sulfuric acid leaching solution, heat, and add acidic leaching residue;
[0020] B, oxidation, blowing compressed air into the leaching tank of step A, oxidizing the slag and liquid in the tank, and closing the compressed air machine after oxidizing and leaching for 18-20 hours;
[0021] C. Filtration: filter the oxidized liquid obtained in step B to obtain dezincification leaching slag and filtrate, send the filtrate to the zinc system to recover zinc, and send the dezincification leaching slag to the lead system to recover silver.
[0022] The heating method is electric heating or steam heating.
[0023] The initial acid concentration of the sulfuric acid leaching solution is 150-180 g / L.
[0024] The heating leaching temperature is at least 95°C.
[0025] The liquid-solid ratio of the sulfuric acid leaching solution to the acid...
Embodiment 1
[0033] In a volume of 100M 3 In the leaching tank, prepare 60M 3 Sulfuric acid solution containing 150g / L of sulfuric acid (weight 60 tons), heated by steam to 95°C, added 7.5 tons of flotation silver concentrate while stirring, opened compressed air (1# air pipe), leached for 18 hours and then filtered. The filter residue weighs 3 tons, the residue contains 18.06% zinc (wt%), the residue rate is 40%, and the zinc leaching rate is 80%.
Embodiment 2
[0035] In a volume of 100M 3 In the leaching tank, prepare 60M 3 Sulfuric acid solution containing 160g / L of sulfuric acid (weight 60 tons), heated by steam to 95°C, adding 6 tons of flotation silver concentrate while stirring, turning on compressed air (1# air pipe), leaching for 18 hours and then filtering. The filter residue weighs 2.4 tons, the residue contains 14.10% zinc (wt%), the residue rate is 40%, and the zinc leaching rate is 82.6%.