Parallel flow type steel billet heating furnace
A billet heating and billet technology, applied in the field of parallel flow billet heating furnace, to achieve the effect of large billet processing, high furnace utilization rate and small floor space
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0014] The parallel-flow steel billet heating furnace of the present invention is as figure 1 Shown, comprise furnace body 4, air supply system, fuel supply system and waste gas exhaust system. The furnace body is a U-shaped structure with double chambers, and the upper ends on both sides of the U-shaped structure are connected with the horizontal structural part 11 . The furnace body is provided with burners 3, and the burners are located on the top of the furnace chamber 5 on both sides, and the number of burners is 6 on each side. The furnace body is provided with a steel billet feed port 2, a steel billet discharge port 13 and a waste gas discharge port. The billet feed port 2 is located at the top of the horizontal structural parts on both sides, the billet discharge port 13 is located at the bottom of the U-shaped structure, and the exhaust gas discharge port is located at the horizontal structural part. Furnace chambers on both sides are provided with conveying device...
Embodiment 2
[0017] Another embodiment of the present invention is as figure 2 As shown, the heating furnace is provided with two billet preheaters 14 and a billet cooler 15 . The billet preheater is connected to the billet feed port 2, and the waste gas discharge ports on both sides are connected to the waste gas discharge system through the billet preheater and the waste gas three-way valve 10. The billet cooler is connected to the billet outlet 13, and the blower 8 is connected to the air inlets 17 of the burners on both sides through the billet cooler 15 and the air three-way valve 9. Other structures are the same as in Embodiment 1. Preheat the heated steel slab 6 to 150-200°C with the residual heat of exhaust gas, and then send it into the heating furnace for heating. The combustion-supporting air is preheated to 200-300° C. by the heat released by cooling the steel billet through the billet cooler 15 , and then goes to the burner 3 for combustion-supporting combustion. Make full...