A construction method and shield belt technology, applied in the direction of earth drilling, tunneling, mining equipment, etc., can solve the problems of ground collapse in the upper railway track and affect the safety of railway operation, so as to ensure operation safety and overcome quicksand collapse Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0029] The present invention will be further described in detail below in conjunction with test examples and specific embodiments. However, it should not be understood that the scope of the above subject matter of the present invention is limited to the following embodiments, and all technologies realized based on the content of the present invention belong to the scope of the present invention.
[0030] The construction method of shield tunneling under pressure for water-rich silt and silt formation under the railway track of the present invention is mainly applied to the water-rich silt and silt formation, including the following steps:
[0031] A. Preparations before tool change:
[0032] Use high-pressure rotary grouting piles to reinforce the soil at the tool change, and learn more about the settlement control standards of the railway main line from the railway department, such as the hourly uplift of the railway line ≤ 2mm; the hourly settlement ≤ 4mm; the cumulative upl...