Method for early warning power grid transmission line mountain fire intelligently in graded mode
A transmission line and mountain fire technology, which is applied in the field of high-level early warning power grid transmission line wild fire, can solve the problems of not being suitable for early warning, not considering the actual situation of power grid transmission lines, etc., to avoid waste of manpower and material resources, improve prevention and control efficiency, and easy to implement Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0047](1) Formulate the early warning level standard for the transmission line of the power grid. The mountain fire warning levels of transmission lines in the entrusted area are divided into five levels according to the principle of heavy to light, with red, orange, yellow, blue and none, which are:
[0048] (1.1), the red warning is the first-level transmission line mountain fire warning. This level of early warning means that the density of fire points monitored by entrusted regional satellites reaches 15 / 10,000 square kilometers or more, or the number of fire points alarms within 3 kilometers on both sides of the entrusted regional power transmission line reaches 50 or more;
[0049] (1.2), the orange warning is the mountain fire warning of the secondary transmission line. This level of early warning means that the density of fire points monitored by entrusted regional satellites reaches 10-15 per 10,000 square kilometers, or the number of fire points alarmed within 3 kil...
Embodiment 2
[0080] Steps (1)~(5) are the same as in Example 1;
[0081] (6) Determine the early warning level of the transmission line mountain fire on the forecast day of the entrusted area. There are different transmission line mountain fire warning levels in the commissioned area on the commissioned forecast day, and the transmission line mountain fire warning level with the largest warning area is taken as the transmission line mountain fire warning level on the commissioned forecast day of the commissioned area;
[0082] Step (7) is the same as in Example 1.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com