A construction method for high pressure tower foundation
A technology of a tower foundation and a construction method, which is applied in the electric power field, can solve the problems of the column sinking, the difficulty of aligning the anchor bolts, and the heavy weight of the anchor bolts, so as to avoid the sinking and ensure the alignment effect.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0030] A construction method for a high-voltage tower foundation, characterized in that it comprises the following steps:
[0031] a sub-pit:
[0032] According to the construction drawings, find out the size of the sub-pit for sub-pit operation, and set up auxiliary piles to facilitate the verification of the central pile;
[0033] b. Earthwork excavation:
[0034] Excavate stepped foundation pits for solid soil and powdery loess, control the width of the bottom plate of the foundation pit, and carry out construction in strict accordance with the construction drawings for the depth of the foundation pit; for over-excavation, the over-excavation part should be paved with stone grouting; for high groundwater levels The foundation pit shall be equipped with pumping equipment to pump out the accumulated water in the pit during construction, and the slope of the pit wall shall be increased;
[0035] During the excavation of the foundation pit, the position and shape of the found...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com