Construction method of large-scale parallel flexible lower-cord combined trusses
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- ZHEJIANG JINGGONG STEEL BUILDING GRP
- Publication Date
- 2015-03-25
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention belongs to the field of steel structure truss construction, and in particular relates to a construction method of a large-scale parallel flexible lower chord composite truss. Background technique
[0002] The spanning distance of long-span roofs is generally increasing, and today's ultra-long-span roofs have reached a spanning level of more than 200 meters. With the continuous breakthrough of the span, it will inevitably bring a series of new technical problems. What kind of material and what type of components should be used to bear and transmit the huge structural internal force caused by the long span, and how to ensure the actual bearing of this material or component? The force state meets the design requirements and so on.
[0003] The lower chord uses multiple parallel-connected large-diameter high-strength steel tie rods to meet the huge internal force requirements of super-long-span trusses, but it also brings complex technical p...