Method for temporary water stopping and soil retaining construction of post-cast strips of basement
A construction method and technology of post-pouring belts, which are applied in water conservancy projects, artificial islands, underwater structures, etc., can solve the problems of delaying the start time of buildings, affecting the normal construction of basements, and water accumulation in foundation pits and basements, so as to prevent Concrete shrinkage or uneven settlement cracking, the effect of shortening the waiting time for backfilling, and shortening the construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0040] In order to better understand the present invention, the present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
[0041] The bottom plate 1 of the basement is fixed on the base plate base, and the base plate base is fixedly connected on the foundation of the basement. The upper surface of the foundation is composed of various reference plane units, and each reference plane unit is located on the same horizontal plane and arranged parallel to each other. The foundation part of the bottom plate includes a concrete cushion layer 2, a waterproof layer 3, and a fine stone concrete protective layer 4 in sequence from bottom to top.
[0042] Such as Figure 1~3 Shown is a basement post-pouring belt temporary water-stop soil-retaining construction method, which mainly includes the following steps:
[0043] Step 1. Construction of 5 water-stop and soil-retaining areas in the post-casting zone of base plate 1:
...