A construction method for temporary water-stop and soil-retaining with post-cast basement

A construction method and technology of post-pouring belts, which are applied in water conservancy projects, artificial islands, underwater structures, etc., can solve the problems of delaying the start time of buildings, affecting the normal construction of basements, and water accumulation in foundation pits and basements, so as to prevent Concrete shrinkage or uneven settlement cracking, the effect of shortening the waiting time for backfilling, and shortening the construction period

Active Publication Date: 2018-10-23
CHINA FIRST METALLURGICAL GROUP
View PDF2 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

During this period, there will be many rainfalls, and the deformation of the foundation pit will be accelerated because it cannot be backfilled; and groundwater and rainwater will flow into the basement from the post-poured belt, resulting in long-term water accumulation in the foundation pit and the basement
For the safety of the foundation pit and the water-free environment in the basement, it is necessary to pump and drain the foundation pit and the basement for a long time, which not only affects the normal construction of the basement, but also increases the construction cost and prolongs the construction period; , which will delay the start time of buildings under construction

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A construction method for temporary water-stop and soil-retaining with post-cast basement
  • A construction method for temporary water-stop and soil-retaining with post-cast basement
  • A construction method for temporary water-stop and soil-retaining with post-cast basement

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0040] In order to better understand the present invention, the present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0041] The bottom plate 1 of the basement is fixed on the base plate base, and the base plate base is fixedly connected on the foundation of the basement. The upper surface of the foundation is composed of various reference plane units, and each reference plane unit is located on the same horizontal plane and arranged parallel to each other. The foundation part of the bottom plate includes a concrete cushion layer 2, a waterproof layer 3, and a fine stone concrete protective layer 4 in sequence from bottom to top.

[0042] Such as Figure 1~3 Shown is a basement post-pouring belt temporary water-stop soil-retaining construction method, which mainly includes the following steps:

[0043] Step 1. Construction of 5 water-stop and soil-retaining areas in the post-casting zone of base plate 1:

...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a method for temporary water stopping and soil retaining construction of post-cast strips of a basement. The method mainly comprises the following steps that 1, water stopping construction at the post-cast strip of a bottom board is carried out, specifically, a bottom board foundation portion is arranged, a pouring formwork of the bottom board is manufactured, bottom board steel bars are arranged in the pouring formwork, a first non-disassembling formwork and a first water stopping steel plate are provided, the first non-disassembling formwork is fixed, and concrete is poured for the bottom board; 2, water stopping and soil retaining construction at the post-cast strip of an external wall, specifically, a blocking precast block mold is manufactured, steel bars are embedded in the precast block mold, pouring of blocking precast blocks is carried out, the embedded steel bars of the blocking precast blocks are spot-welded to a post-cast strip reinforcing mesh on the external wall, a waterproof coiling material is laid on the upper surface of each blocking precast block, and backfilling of the periphery of a foundation pit is carried out; and 3, water stopping construction at the post-cast strip of a floor. The method has the beneficial effects that the water-free environment in the basement is ensured by carrying out temporary closed water stopping construction on the post-cast strips of the basement bottom board, the external wall and the floor, the number of construction procedures is small, the construction period is shortened, and the construction cost is reduced.

Description

technical field [0001] The invention relates to the technical field of basement construction, in particular to a construction method for a basement post-cast belt for temporary water and soil retention. Background technique [0002] In construction engineering, the basement is a very important and common part. It is mainly used for garage parking or business. The backfilling around the foundation pit can only be done after the basement post-casting tape is constructed. It takes a long time from the start of the foundation pit support construction to the completion of the basement post-pouring belt. The foundation pit support works for too long before the foundation pit is backfilled, and there are certain safety hazards. For example, when the basement post-pouring belt is not poured, the groundwater will Seep into the basement from the rear pouring zone of the floor, and rainwater will also flow into the basement from the rear pouring zone of the outer wall and floor (roof),...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D29/16E02D31/02E04B1/68
CPCE02D29/16E02D31/02E04B1/68
Inventor 邵正东盛振斌郭继舟李少祥
Owner CHINA FIRST METALLURGICAL GROUP