A technology of burying in soil and construction method, applied in basic structure engineering, construction and other directions, can solve the problems of reduced structural safety, difficult control of the direction and verticality of steel columns, poor structural integrity, etc., to improve construction accuracy, The effect of improving structural construction quality and establishing structural safety
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0027] Such as Figure 1-2 As shown, a construction method for controlling the direction and verticality of the column pile buried in the soil comprises the following steps:
[0028] 1. Locate the pile position on the hardened concrete floor 7, release the direction control line 11 near the pile position, place two tripods 13 on the control line of theodolite 16, and pass the centering rod 15 on the two tripods 13 through the line The rope 14 is connected, and the centering rod 15 on one tripod in the two tripods 13 is arranged on the control line 11;
[0029] 2. Set the pile site, use the rotary excavator to align the pile hole 12 on the concrete floor 7 to be built, use the truck crane to lift the pile driver, align the drill bit of the pile driver with the pile hole 12, and check the levelness of the pile frame , vertical correction, the pile driver and the pile driver drill bit are installed to meet the requirements and drill the pile hole. After the drilling is completed...