Pile-supported and rigidity-varied reinforced cushion composite foundation and construction method thereof
A technology of reinforced cushion and composite foundation, which is applied in foundation structure engineering, sheet pile wall, building, etc., can solve the problems of insufficient soil bearing capacity between piles, limited height of embankment, difficult to control settlement, etc. The effect of reducing differential settlement of pavement and ensuring the quality of piles
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0057] The thickness of soft soil in a site is 11m, including silt, silty fine sand, and clay layer. The length of the pile designed by the present invention is 16m, and the prestressed pipe pile is used. The pile diameter is 400mm and the distance is 2.5m. The sandy clay layer is 5m. After the site is leveled, a 200mm thick sandstone layer 2 is laid; after leveling and compaction, the first layer of geogrid 31 is laid; Lay the second layer of geogrid 33 after solidification, pave the 150mm thick cement stabilized crushed stone layer 4 on the second layer of geogrid 33, and compact it; Fill the soil layer or directly set the surface layer to build grain depots, storage yards, etc., which meet the design functional requirements.
[0058] In the formation process of the rigid pile composite ground base 1 in this embodiment, the pipe pile ends pass through the soil layer with high compressibility, and enter the soil layer with relatively low compressibility and good properties, a...
Embodiment 2
[0060] It is proposed to build a high-grade highway of 100km in the soft soil area, with a base width of 20m. Assuming that the foundation treatment uses the deep mixing pile method and the pile spacing is the usual 1.2m, 1.4 million piles will be needed, and an investment of 700 million yuan will be required for the pile alone. But if design according to the achievement of the present invention, under the situation that guarantees driving safety, pile spacing is suitably adjusted large, then ground treatment expense can be significantly reduced. According to calculations, if the pile spacing is adjusted to 2.5-3.0m, the investment rate can be reduced by 30%-40%, and the construction quality of the pile body can also be guaranteed.
Embodiment 3
[0062] A test section of an expressway, with a total length of 148.5m, is divided into four tender sections. The four sections are treated in different ways. Each section is equipped with key sections and buried monitoring instruments.
PUM
Property | Measurement | Unit |
---|---|---|
Thickness | aaaaa | aaaaa |
Particle size | aaaaa | aaaaa |
Particle size | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com