Calculation method and calculation apparatus for general-drawing earthwork volume of oil and gas storage and transportation station
A calculation method and a technology of a calculation device, applied in calculation, image data processing, instruments, etc., can solve the problems of result error, no way, and no way to reflect the estimation process in a more intuitive way, so as to reduce errors and improve The effect of precision
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0043] Embodiment 1, a method for calculating the earthwork quantity of the general plan of an oil and gas storage and transportation station described in the first embodiment of the present invention, the method includes: using a three-dimensional design platform to calculate the earthwork quantity of the general plan site and using the three-dimensional The calculation method of the earthwork quantity of the general drawing structure on the design platform;
[0044] in,
[0045] like figure 1 As shown, the calculation method of the earthwork volume of the site using the 3D design platform includes:
[0046] Step A1, obtaining the two-dimensional or three-dimensional terrain data of the oil and gas storage and transportation station, using the terrain processing tool of the CIVIL 3D three-dimensional design platform to convert the two-dimensional or three-dimensional terrain data to obtain the original topographic map of the oil and gas storage and transportation station;
...
Embodiment 2
[0059] Embodiment 2, a calculation device for the earthwork quantity of the general plan of oil and gas storage and transportation stations according to the second embodiment of the present invention is characterized in that it includes: a calculation device for the earthwork quantity of the general plan site using a three-dimensional design platform and a three-dimensional design platform. The design platform is used to calculate the earthwork quantity of the structure of the general plan;
[0060] in,
[0061] The calculation device for the earthwork volume of the site using the 3D design platform includes:
[0062] The original topographic map forming device is used to obtain the two-dimensional or three-dimensional topographic data of the oil and gas storage and transportation station, and use the terrain processing tool of the CIVIL3D three-dimensional design platform to convert the two-dimensional or three-dimensional topographic data into the original topographic map of...