Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Construction method for artificial hole-digging grouting pile

A technology of manual digging and construction methods, applied in sheet pile walls, foundation structure engineering, construction, etc., can solve problems such as pile center deviation, weak connection between upper retaining wall and lower retaining wall, complex engineering geology, etc., and reduce construction errors , Improve the strength and improve the effect of safety

Active Publication Date: 2017-07-07
HUAYU CONSTR GROUP
View PDF3 Cites 13 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, the construction of manual digging piles requires operators to carry out hole-forming operations underground for a long time. Due to the complex geology of many projects, it is an important auxiliary measure for the construction of manual digging piles in the well wall protection
In the existing construction, the lower retaining wall is generally poured after the concrete has hardened after the pouring of the upper retaining wall is completed. Since the concrete of the upper retaining wall and the concrete of the lower retaining wall harden successively, the connection between the upper retaining wall and the lower retaining wall is relatively weak. Pile center deviation is prone to occur under pressure

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for artificial hole-digging grouting pile
  • Construction method for artificial hole-digging grouting pile
  • Construction method for artificial hole-digging grouting pile

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0026] Example: such as figure 1 Shown, a kind of manual excavation hole filling pile construction method comprises the following steps:

[0027] (1) At the positioning point of the artificially dug hole grouting pile determined by the design, the hole shall be dug manually. When the depth reaches 0.8m-1m, the reinforced concrete well circle shall be poured, and the top surface of the well circle shall be 100mm-150mm higher than the site.

[0028] (2) For the construction of pile hole wall protection, the wall protection formwork is installed every time the pile hole is dug 1 meter deep. The wall protection formwork is repeatedly used by removing the upper section and supporting the lower section. The small end of the formwork is on the top, and the big end is on the bottom. When the retaining wall formwork is installed, the concrete retaining wall is poured.

[0029] like figure 2 As shown, before installing the retaining wall template, a trench 2 is excavated downward at ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
particle diameteraaaaaaaaaa
Login to View More

Abstract

The invention relates to the technical field of building construction, in particular to a construction method for an artificial hole-digging grouting pile. The construction method comprises the following steps that firstly, hole digging is conducted at a designed and determined artificial hole-digging grouting pile positioning point in an artificial hole digging manner, and pouring of a reinforced concrete well ring is conducted; secondly, pile hole protection wall construction is conducted, and before a protection wall template is installed, the bottom of a pile hole is downwards excavated to form a groove, and a connecting assembly connecting an upper protection wall with a lower protection wall is placed in the groove; thirdly, pile end expansion head construction is conducted; fourthly, the protection wall template is dismounted, and a reinforcement cage is hung and placed down; and fifthly, grouting pile pouring is conducted, concrete is pumped to a material barrel port through a concrete pump and pumped to the hole bottom through a material barrel via communication, and the concrete is vibrated densely through a concrete vibration machine. According to the construction method, the strength of the protection walls can be greatly improved, the anti-pressure ability that the protection walls resist a soil layer is improved, the protection walls have enough strength and stability and adapt to construction of soft soil texture, and the safety of the construction environment is improved; and the construction error between the upper protection wall and the lower protection wall can be reduced, and the precision of the pile center position and perpendicularity can be guaranteed.

Description

technical field [0001] The invention relates to the technical field of building construction, in particular to a method for manually digging a cast-in-place pile. Background technique [0002] The artificial excavation pile is relative to the bored pile column, which is the operation method of artificially excavating the soil to form the hole. Manual hole-digging piles are the simplest and most reliable form of pile foundation in all pile foundation constructions, and are favored by engineering circles. However, the construction of manual excavated piles requires operators to carry out hole-forming operations underground for a long time. Due to the complex geology of many projects, it is an important auxiliary measure for the construction of manual excavated piles during the well wall protection. In the existing construction, the lower retaining wall is generally poured after the concrete has hardened after the pouring of the upper retaining wall is completed. Since the con...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/38E02D5/44C04B28/04C04B22/10C04B103/12
CPCC04B28/04C04B40/0039E02D5/38E02D5/44E02D2250/0023C04B22/06C04B22/10C04B22/064C04B14/06C04B14/02
Inventor 孙俊方志慧李艳
Owner HUAYU CONSTR GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products