A kind of construction method of CFG pile

A construction method and technology of construction steps, applied in sheet pile walls, foundation structure engineering, construction, etc., can solve problems such as long construction period, and achieve the effects of saving construction period, prolonging service life and shortening construction period

Active Publication Date: 2019-01-29
BEIJING ZHONGRUN BAOCHENG ENG TECH CO LTD
View PDF3 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0007] In short, with this kind of construction technology, it takes about two weeks after the CFG pile foundation concrete pouring is completed and before the pile foundation inspection, the construction period is long

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A kind of construction method of CFG pile
  • A kind of construction method of CFG pile
  • A kind of construction method of CFG pile

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0056] A construction method of a CFG pile includes the following construction steps.

[0057] Step 1. Leveling the site: clearing the soil and obstacles on the surface;

[0058] Step 2, measuring and setting out: release the specific position of each pile according to the coordinates and mark it;

[0059] Step 3, the pile driver is in place: make the drill pipe 22 of the long auger rig 2 vertically aligned with the center of the pile position, control the drilling, and measure the verticality of the hole by hanging a vertical ball on the drill stand, or use the rig to automatically Equipped with a verticality adjuster to ensure that the verticality deviation of the drill pipe meets the process requirements;

[0060] Step 4, drilling:

[0061] Such as figure 2 As shown, before drilling, make a stop pump mark 6 and a drilling completion mark 7 on the stand 21, and first lead the motor top surface 24 horizontally to the stand 21 to make a reference mark 5; a distance below t...

Embodiment 2

[0073] The difference from the first embodiment is that the observation hole 9 is set on the drill pipe 22 to control the time to stop the pumping material, so that the length of the overfilling pile head is uniformly s. Observation hole 9 is offered in the middle of two layers of helical blades 26 near the position of upper helical blades (refer to Figure 10 ).

[0074] Proceed as follows:

[0075] Before drilling in step 4, calculate h, the opening of the rod wall: as Figure 8 Shown, calculate the height h of the required concrete in the drill pipe 22 for the super-filling pile head, and offer the observation hole 9 that can flow out the concrete slurry on the drill pipe side wall above the drill pipe bottom 23 h position. The calculation formula is as follows: h=(s+n)*R 2 / r 2 , where s is the length of the overfill pile head, and 0.5m≤s≤1.2m, the specific value of s is determined before drilling; n is any number ≥ 0, and the value of n can satisfy h≥ ground elevation...

Embodiment 3

[0083] The difference from the second embodiment is that, as Figure 11 As shown, if the calculated hH, and it does not need to be too large. Preferably n can be equal to 1 or 2. Now take n=1 as an example for illustration:

[0084] Assuming H=8m, s=1m, the radius R of hole pile 4 is 0.2m, and the inner diameter r of the drill pipe is 0.08m, the calculated h=(1+1)*0.2 2 / 0.08 2 =12.5m, h(12.5m)>H(8m), according to h=12.5m, the observation hole 9 is set on the drill pipe 22, then the observation hole 9 can leak 4.5m from the ground, and the workers can observe that the concrete flows out of the hole.

[0085] At the same time, because c=original ground elevation 11-design pile top elevation 13+n, so the position of suspension pole pulling mark 8 should be lowered by n=1 meter.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of a CFG pile. The construction method is characterized in that the construction method comprises the following construction steps: leveling land, carrying out measurement and setting out, putting a piling machine in place, drilling, pumping concrete, pulling a rod, stopping pumping, pulling the rod, shifting a drilling machine, excavating a foundation pit, removing soil surrounding the pile, cutting off a pile head, detecting a pile foundation and constructing a mattress layer. By adopting the construction method, the excavation of the foundation pit can be carried out at the same time of waiting for the concrete strength to rise before the pile foundation detection, so that the construction period is shortened substantially.

Description

technical field [0001] The invention relates to the technical field of CFG piles, in particular to a construction method of CFG piles. Background technique [0002] CFG piles are cement fly ash gravel piles, which are mixed with crushed stones, stone chips, sand, and fly ash mixed with cement and water. Various drilling machines are used to make holes first, and then concrete is poured into piles. The pile diameter of CFG piles is generally 350-600mm, and the distance between the pile centers is 3~5 times of the pile diameter. [0003] According to different geology, there are four main construction techniques for CFG piles, namely, long auger drilling and pouring into piles, mud retaining wall drilling and pouring into piles, long auger drilling, in-pipe pumping concrete piles, and immersed tube pouring into piles. Among them, the method of long auger drilling and pumping concrete piles in the pipe is suitable for foundations such as cohesive soil, silt, and sandy soil. Th...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D5/36
CPCE02D5/36
Inventor 陈世成冯军峰
Owner BEIJING ZHONGRUN BAOCHENG ENG TECH CO LTD