Tunnel bolt-shotcrete support concrete integrated pouring formwork and construction method thereof
A construction method and concrete technology, applied in tunnels, tunnel linings, earthwork drilling, etc., can solve the problems of time-consuming and waste
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0019] Further detailed explanation through specific implementation mode below:
[0020] The reference signs in the drawings of the specification include: arc-shaped steel structure 1 and jacking mechanism 2 .
[0021] The implementation of concrete integral pouring formwork and construction method for tunnel anchoring and spraying support is basically as follows figure 1 and figure 2 As shown, the specific steps are as follows:
[0022] Step 1: Treat the surface of the sprayed rock. Generally, the floating dust and cuttings on the sprayed rock surface are washed with high-pressure water.
[0023] Step 2: Concrete mixing and transportation. Wet shotcrete mixing adopts fully automatic metering forced mixer, and transportation adopts concrete transport tank trucks, which are mixed as they are transported. When spraying concrete, multiple transport vehicles should alternately transport materials according to the actual construction situation. Meet the supply of wet shotcrete....