Construction method of deep and high permeable layer foundation pit dewatering structure
A construction method and technology of water seepage layer, applied in infrastructure engineering, excavation, construction, etc., can solve the problems of high precipitation costs, great impact on the surrounding soil environment, long construction period of foundation engineering, etc., and achieve the effect of saving costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0017] A construction method for a foundation pit dewatering structure in a deep and highly permeable water layer, comprising the following steps:
[0018] S1. Vertical curtain construction: In the deep and strong permeable layer foundation, a rectangular vertical curtain 10 is formed through the eccentric occlusal pile foundation construction method;
[0019] Wherein, the eccentric occlusal pile foundation construction method includes the following steps,
[0020] S11. Make a concrete guide wall to ensure the accurate positioning of the occlusal piles, ensure the stability of the drilling rig, and bear the construction load;
[0021] S12. The arrangement of the occlusal piles is an unreinforced ultra-retarded concrete pile (A pile) and a reinforced concrete pile (B pile) at intervals. The A pile is constructed first, followed by the B pile. The construction of Pile B was completed before the coagulation. Both Pile A and Pile B were constructed with full-casing drilling rigs,...
Embodiment 2
[0026] A construction method for a foundation pit dewatering structure in a deep and highly permeable water layer, comprising the following steps:
[0027] S1. Vertical curtain construction: In the deep and strong permeable layer foundation, a rectangular vertical curtain 10 is formed through the eccentric occlusal pile foundation construction method;
[0028] Wherein, the eccentric occlusal pile foundation construction method includes the following steps,
[0029] S11. Make a concrete guide wall to ensure the accurate positioning of the occlusal piles, ensure the stability of the drilling rig, and bear the construction load;
[0030] S12. The arrangement of the occlusal piles is an unreinforced ultra-retarded concrete pile (A pile) and a reinforced concrete pile (B pile) at intervals. The A pile is constructed first, followed by the B pile. The construction of Pile B was completed before the coagulation. Both Pile A and Pile B were constructed with full-casing drilling rigs,...
Embodiment 3
[0035] A construction method for a foundation pit dewatering structure in a deep and highly permeable water layer, comprising the following steps:
[0036] S1. Vertical curtain construction: In the deep and strong permeable layer foundation, a rectangular vertical curtain 10 is formed through the eccentric occlusal pile foundation construction method;
[0037] Wherein, the eccentric occlusal pile foundation construction method includes the following steps,
[0038] S11. Make a concrete guide wall to ensure the accurate positioning of the occlusal piles, ensure the stability of the drilling rig, and bear the construction load;
[0039] S12. The arrangement of the occlusal piles is an unreinforced ultra-retarded concrete pile (A pile) and a reinforced concrete pile (B pile) at intervals. The A pile is constructed first, followed by the B pile. The construction of Pile B was completed before the coagulation. Both Pile A and Pile B were constructed with full-casing drilling rigs,...