A method for in-situ overhead installation of auxiliary brackets for integral ballast bed reinforcement
An integrated ballast bed and installation auxiliary technology, applied in the directions of roads, tracks, ballast layers, etc., can solve the problems of difficulty in binding steel bars with main reinforcement hoops, unfavorable flow operations, and difficulty in ensuring quality, and achieve convenient binding, good control, and shortening. The effect of the construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0028] The specific implementation of the present invention will be described in detail below in conjunction with the accompanying drawings. As a part of this specification, the principles of the present invention will be described through examples. Other aspects, features and advantages of the present invention will become clear through the detailed description. In the referenced drawings, the same reference numerals are used for the same or similar components in different drawings.
[0029] The present invention is applied to the airport north vehicle depot of Shenzhen International Convention and Exhibition Center's supporting municipal project. The site is located in the north of Bao'an Airport and in the land west of the airport north parking lot on Line 11. The permanent land area of the vehicle depot is about 15.6675 hectares, and the temporary land area is 2.8675 hectares, the plot is planned to be used for airport development. like Figure 1 to Figure 4 Shown, the ...