Fire control system for bulging testing of containment of nuclear power plant and configuration method of fire control system

A fire-fighting system and pressure test technology, which is applied in nuclear power generation, nuclear engineering, emergency protection devices, etc., can solve the problem that the containment pressure test of the cold-state function test cannot be completed, the cold-state function test cannot be carried out as planned, and the commissioning progress of the nuclear power plant is affected. and other issues, to achieve the effect of short equipment debugging cycle, high economy and practicability, and low additional cost

Inactive Publication Date: 2019-01-25
中广核工程有限公司 +2
View PDF6 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The construction of a nuclear power plant is an extremely large and complex system project. Various problems may be encountered during the construction process, which may cause the cold-state functional test to be unable to proceed as planned. Satisfying the requirements but not having the starting conditions, resulting in the inability to complete the cold-state functional test and containment pressure test, affecting the overall commissioning progress of the nuclear power plant, thereby affecting the final commercial operation

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Fire control system for bulging testing of containment of nuclear power plant and configuration method of fire control system
  • Fire control system for bulging testing of containment of nuclear power plant and configuration method of fire control system
  • Fire control system for bulging testing of containment of nuclear power plant and configuration method of fire control system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 2

[0075] like image 3 As shown, Embodiment 2 of the present invention provides a method for configuring a fire-fighting system during a nuclear power plant containment pressure test, which is applicable to the fire-fighting system shown in Embodiment 1. The configuration method includes:

[0076] Step S1, providing a source of fire-fighting water through the high-level water tank;

[0077] Step S2, connecting the high-level water tank to the pipelines of the containment sprinkler system and the nuclear island fire protection system through temporary pipelines, so as to introduce fire-fighting water through the pipelines of the containment sprinkler system and / or nuclear island fire protection system inside the containment;

[0078] Step S3, setting at least two delivery pumps connected in parallel on the temporary pipeline to deliver fire-fighting water;

[0079] Step S4, simultaneously connecting at least two temporary power sources to each of the delivery pumps to provide r...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a fire control system for bulging testing of a containment of a nuclear power plant and a configuration method of the fire control system. The fire control system comprises a containment spray system, a nuclear island fire extinguishing system and a standby fire extinguishing system, wherein the standby fire extinguishing system comprises an overhead tank, a temporary pipeline, at least two conveying pumps and at least two temporary power supplies, wherein the overhead tank is used for providing a fire water source; one end of the temporary pipeline is connected with theoverhead tank, and the other end of the temporary pipeline is connected with pipelines of the containment spray system and the nuclear island fire extinguishing system separately so as to introduce fire water into the containment; the at least two conveying pumps are connected in parallel and are arranged on the temporary pipeline so as to convey the fire water; each temporary power supply is simultaneously connected with the at least two conveying pumps so as to provide a redundant power supply. According to the fire control system for bulging testing of the containment of the nuclear powerplant and the configuration method of the fire control system, provided by the invention, available resources of the nuclear power plant are utilized, the equipment debugging cycle is short, the costis low, and thus, the fire control system and the configuration method thereof have relatively high economical efficiency and practicability.

Description

technical field [0001] The invention relates to the technical field of fire-fighting systems, in particular to a fire-fighting system and a configuration method thereof used during a containment pressure test of a nuclear power plant. Background technique [0002] The containment vessel of a nuclear power plant is the third barrier to prevent the leakage of fission products, and is used to contain radioactive materials and shield radiation under operating conditions and accident conditions. According to the design requirements, the containment vessel of a nuclear power plant needs to undergo a containment compression test (CTT) during the commissioning phase during construction, the first overhaul after commercial operation, and every ten years to verify whether the overall sealing and mechanical strength of the containment vessel meet the design requirements . During the containment pressure test, the internal pressure of the containment is relatively high, and the oxygen ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): G21C9/04G21C9/06
CPCG21C9/04G21C9/06Y02E30/30
Inventor 翟巴菁赵春光李西安赵鑫闫明晶徐立研
Owner 中广核工程有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products