Multi-terminal flexible interconnection power distribution network planning method and system

A technology for distribution network planning and multi-terminal flexibility, applied in data processing applications, forecasting, instruments, etc., can solve problems such as difficulty in accepting a large number of DGs into the network, abandoning wind and light, and failing to maximize benefits.

Inactive Publication Date: 2019-05-10
STATE GRID JIANGSU ELECTRIC POWER CO ELECTRIC POWER RES INST +4
View PDF0 Cites 13 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] At this stage, DG operators fail to fully consider the planning and development of the distribution network when planning, and are limited by the capacity of the power flow section, resulting in serious problems of abandoning wind and light; grid companies do not fully consider the possible planning of DG when investing in construction , which also makes the planning of the distribution network unreasonable, it is difficult to accept a large number of DG into the network, and it is impossible to maximize the benefits; in addition to investing in construction, the power grid company can also implement various demand side response (demand side response, DSR) projects to encourage ESS and FL Waiting for power users to adjust their power consumption behavior will also affect distribution network investment and DG access

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Multi-terminal flexible interconnection power distribution network planning method and system
  • Multi-terminal flexible interconnection power distribution network planning method and system
  • Multi-terminal flexible interconnection power distribution network planning method and system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0058] The present invention will be further described below in conjunction with the accompanying drawings. A method for planning a multi-terminal flexible interconnection distribution network, comprising the following steps:

[0059] 1. With the goal of maximizing the annual comprehensive income of distributed power supply operators, flexible load users and energy storage users, the simulated annealing algorithm is used to carry out the pre-established location and capacity model of distributed power supply, flexible load and energy storage systems solve.

[0060] From the perspective of economy, aiming to maximize the annual comprehensive income of distributed generation (DG) operators, determine the installation location and capacity of DG. The objective function is as follows:

[0061]

[0062]

[0063]

[0064]

[0065]

[0066] In the formula: are the annual electricity sales income, annual subsidy income, ancillary service annual income, annual operati...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a multi-terminal flexible interconnected power distribution network planning method and system, and the method comprises the steps: considering the interaction among a source,a network, a load and a storage, coordinating the respective benefit demands of a distributed power supply operator, a power grid company and a power user, combining the system planning with the operation optimization, and proposing a source-network-load-storage three-layer coordinated planning model for a multi-terminal flexible interconnected power distribution network, processing the uncertainty problem of the distributed power supply and the load by using a scene analysis method, and solving the model by using a hybrid algorithm formed based on a simulated annealing algorithm and an interior point method. According to the invention, benefit requirements of different subjects are considered, friendly interaction of a source, a network, a load and storage is promoted, respective benefitsof a DG operator and a power user are guaranteed, the operation level of the system can be improved, and the power supply quality and economy of system operation are improved.

Description

technical field [0001] The invention belongs to the technical field of active distribution network planning, and in particular relates to a multi-terminal flexible interconnection distribution network planning method and system. Background technique [0002] With the development of back-to-back flexible DC (Back-to-Back VSC-HVDC) technology, it has become an important development trend to use flexible power electronics technology to transform distribution networks. Applying the back-to-back flexible straight technology to the AC distribution network can change the long-term practice of "closed-loop design and open-loop operation" in my country's distribution network. It can not only realize the long-term safe closed-loop operation of any feeder in the distribution network, but also accurately control the power grid Trend distribution. The flexible interconnection operation of distribution network is an important way to improve the reliability of power supply and promote the ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G06Q10/04G06Q10/06G06Q50/06
Inventor 韩华春葛乐张伟李强吕振华
Owner STATE GRID JIANGSU ELECTRIC POWER CO ELECTRIC POWER RES INST
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Eureka Blog
Learn More
PatSnap group products