Method and device for determining construction technology scheme of long piled wharf project

A high-pile wharf and construction technology technology, which is applied in the field of port engineering, can solve problems such as inaccurate construction technology schemes of high-pile wharf engineering, and achieve the effects of saving costs, saving construction time, and improving accuracy

Active Publication Date: 2019-09-20
WATER TRANSPORT PLANNING & DESIGN INST
View PDF3 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] The embodiment of the present invention provides a method and device for determining the construction technology scheme of the high-pile wharf project, so as to at least solve the problems caused by the existing method of predicting and analyzing the construction process of the high-pile wharf project based on construction experience. inaccurate technical issues

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method and device for determining construction technology scheme of long piled wharf project
  • Method and device for determining construction technology scheme of long piled wharf project
  • Method and device for determining construction technology scheme of long piled wharf project

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0032] According to an embodiment of the present invention, an embodiment of a method for determining a high-pile wharf project construction process scheme is provided. It should be noted that the steps shown in the flow chart of the accompanying drawings can be implemented in a computer system such as a set of computer-executable instructions and, although a logical order is shown in the flowcharts, in some cases the steps shown or described may be performed in an order different from that shown or described herein.

[0033] figure 1 It is a flow chart of a method for determining the construction process scheme of a high-pile wharf project according to an embodiment of the present invention, such asfigure 1 As shown, the method includes the following steps:

[0034] Step S102, acquiring engineering information of the high-pile wharf engineering.

[0035] In step S102, the engineering information of the high-pile wharf project includes at least one of the following: sub-item ...

Embodiment 2

[0067] According to an embodiment of the present invention, an embodiment of a device for determining a construction process scheme of a high-pile wharf project is also provided, wherein, Figure 4 It is a schematic diagram of a device for determining the construction process scheme of a high-pile wharf project according to an embodiment of the present invention, as Figure 4 As shown, the device includes: an acquisition module 401 , a simulation module 403 and an optimization module 405 .

[0068] Among them, the acquisition module 401 is used to obtain the engineering information of the high-pile wharf project; the simulation module 403 is used to simulate the construction process of the high-pile wharf project based on the engineering information, and obtain the initial construction project of each sub-item during the construction process. Construction process plan information; optimization module 405, used to optimize the construction process based on the initial construct...

Embodiment 3

[0078] According to another aspect of the embodiments of the present invention, there is also provided a storage medium, the storage medium includes a stored program, wherein, when the program is running, the device where the storage medium is located is controlled to execute the high-pile wharf engineering construction process scheme in Example 1 method of determination.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a method and device for determining a construction technology scheme of a long piled wharf project. The method comprises the steps: project information of the long piled wharf project is obtained; the construction process of the long piled wharf project is simulated based on the project information, and initial construction technology scheme information of all division component construction projects in the construction process is obtained; and the construction process is optimized based on the initial construction technology scheme information, and the target construction technology scheme of all the division component construction projects is obtained. The technical problem that as for an existing method for predicting and analyzing the construction process of the long piled wharf project according to the construction experience, the construction technology scheme of the long piled wharf project is inaccurate is solved.

Description

technical field [0001] The invention relates to the technical field of port engineering, in particular to a method and a device for determining a construction process scheme of a high-pile wharf project. Background technique [0002] The high-pile wharf project is a key control project in the port construction project. It has the characteristics of large investment, long period, and complex construction management. , Intelligent decision-making management. [0003] However, the planning and arrangement of high-piled wharf projects are easily affected by random factors, and it is difficult to analyze and study them using analytical methods. At present, there are few studies on the application of computer simulation technology for port engineering construction management, and even less research on high-piled wharf construction projects. [0004] At present, the planning of the construction method and construction organization of the high-piled wharf project is mainly based o...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E02B3/06
CPCE02B3/068
Inventor 杨国平商剑平邰世文毕磊郑天立郭享刘春泽唐颖柳海宇
Owner WATER TRANSPORT PLANNING & DESIGN INST
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products