Reinforced concrete bridge suspension anchor type operation platform and construction method thereof
A reinforced concrete, operating platform technology, applied in bridges, bridge maintenance, bridge reinforcement and other directions, can solve the problems affecting the use function and service life of bridges, the difficulty of bridge maintenance and reinforcement construction, the impact of the environment and construction period, etc. Strength, easy to purchase, good safety and stability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0059] as attached figure 1 As shown, the operation process of the present invention mainly includes: construction preparation; setting up a floor-standing operation platform; positioning drilling; injecting glue, installing expansion bolts; anchoring vertical poles; erecting longitudinal and horizontal bars; laying scaffolding boards; Installation; inspection and acceptance.
[0060] combined with Figure 1-19 Shown, a kind of reinforced concrete bridge suspended anchor type operating platform construction method of the present invention, its concrete steps are as follows:
[0061] Step 1: Use steel pipes to build a floor-standing scaffolding operation platform near the bottom of the side beam of the abutment; before setting up the operation platform, the ground at the platform position should be leveled and compacted, and drainage facilities should be prepared. The lower part is equipped with sweeping rods, and scissors are added on the three facades outside the scaffoldin...
Embodiment 2
[0074] The difference from Example 1 is that as a further optimization of the solution of the present invention, step 3 uses an air compressor to blow out dust; step 7 is to install spring washers outside the bolts, and then tighten the nuts; the transverse length of the working platform is greater than the width of the bridge by 1.5m , the longitudinal length is greater than the bridge width 3m, and the scissors brace angle is 60°; the pull-out bearing capacity detection data of the step 8 pull-out test is 8KN; the overlapping length of the longitudinal bar 4 and the cross bar 5 described in the step 9 is 1500mm, When the fasteners of the nodes of the cross bar are clamped, the gap at the opening is 1 mm, and the fastening torque of the fasteners is 60 N m; the scaffold board in step 10 is a bamboo fence board; the protective railings 6 around the operating platform are erected with steel pipes, and the erection height is 2 m ; The distance between the poles is 1.0m; the heigh...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com