Embodiment 1
[0062] A structural diagram of a coastal multi-source and multi-load coordinated control system considering seawater desalination provided by the present invention is shown in figure 1 shown, including:
[0063] Control centers, new energy power stations, energy storage devices, seawater desalination facilities and conventional loads;
[0064] New energy power stations, energy storage devices, seawater desalination facilities and conventional loads are respectively connected to the control center by communication, and are used to collect their own operating data and send them to the control center, and receive control signals from the control center;
[0065] New energy power stations, energy storage devices, seawater desalination facilities and conventional loads are electrically connected to the busbar, and the busbar is connected to the distribution network through tie lines;
[0066] The control center is used to formulate the optimal day-ahead plan and optimal intra-day ...
Embodiment 2
[0080] Based on the same inventive concept, the present invention also provides a coastal multi-source and multi-load coordinated control method considering seawater desalination. This method controls the control system as shown in Embodiment 1.
[0081] The method flow is as follows image 3 shown, including:
[0082] Step 1: According to the data required for formulating the plan ahead, predict the output of the new energy power station, the load power of the conventional load and the demand for desalinated water the next day;
[0083] Step 2: Input the next day's new energy power station output, conventional load power and desalinated water demand into the pre-established coordination optimization model to obtain the optimal day-ahead plan;
[0084] Step 3: When the next day arrives, based on the optimal day-ahead plan, formulate the optimal intra-day plan and control the energy storage device and seawater desalination facility to implement the optimal intra-day plan, and...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com