A water-rich sand layer and construction method technology, which is applied in earthwork drilling, infrastructure engineering, shaft equipment, etc., can solve problems such as inability to excavate, cutter head wear, and construction difficulties, and achieve excellent long-term strength and durability, The effect of saving construction cost and avoiding soil disturbance
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0049] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0050] Such as figure 1 and figure 2 As shown, the method includes:
[0051] Step 1. Clean up the gravel and debris in the construction site, level the construction site, and compact and harden the construction site.
[0052] Step 2. Design the position of the longitudinal probe hole 2 along the tunnel centerline 1. The diameter of the longitudinal probe hole 2 is φ800mm, the hole distance is 750mm, and the occlusal width is 50mm. By analogy, the position of the horizontal clearance hole 3 is confirmed according to the position of the longitudinal probe hole 2. The diameter of the horizontal clearance hole 3 is φ800 mm, and the hole distance is 1300 mm. out), and add a sub-serial number on the basis of the number of the longitudinal probe hole 2 as the number of the horizontal clearance hole 3. 2#, 1-3#, 1-4#, and so on, are used...
PUM