Construction method of anti-seepage walls for entanglement-containing strata or wasteyard strata
A construction method and technology of anti-seepage wall, applied in sheet pile wall, foundation structure engineering, earth mover/shovel and other directions, can solve the problems of inability to form grooves, large pores, large grouting volume, etc., and achieve the on-site environment Strong adaptability, good anti-seepage effect and high wall quality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0025] The following is attached figure 1 , to further illustrate a specific embodiment of the construction method of the present invention for a cut-off wall in a stratum containing entanglements or a refuse ground stratum. A construction method of the present invention for a cut-off wall in a formation containing entanglements or a refuse ground is not limited to the description in the following embodiments.
[0026] This embodiment provides a kind of specific implementation mode for the construction method of the anti-seepage wall of the stratum containing entanglements or the stratum of the garbage site, such as figure 1 shown, including the following steps:
[0027] (1) Excavate the foundation trench according to the axis position of the cut-off wall. The foundation groove is located above the axis of the anti-seepage wall, and is mainly used to solve the residual slurry storage and return slurry supply during the milling and excavation operation. Usually, its length sh...