Asphalt pavement repairing method and asphalt pavement structure
A technology for asphalt pavement and road shoulder, which is applied in the field of asphalt pavement structure and asphalt pavement repair, can solve the problems of high-speed traffic impact and long construction time, and achieves the effect of simple construction, convenient material selection and construction time saving.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0030] At present, the pumping treatment often adopts the local base reinforcement method, but because the original pumping location is mostly in the water area of the asphalt pavement, the local base reinforcement treatment cannot completely solve the pumping problem in this area. Under the action of frequent water accumulation, there will still be pumping phenomenon around the repaired part.
[0031] For this reason, the present embodiment provides a kind of asphalt pavement repairing method, bury hemp rope 100 in the surface course 1 place of asphalt pavement pumping scope, and make the end of hemp rope 100 extend to the road shoulder side slope place, make surface course 1 Seepage is discharged from the road surface, so as to ensure that the repaired part will not be damaged by secondary pumping.
[0032] Concretely, described asphalt pavement patching method, comprises the following steps:
[0033] (1) if figure 1 and 2 As shown, for the grouting part of the road sur...
Embodiment 2
[0039] This embodiment provides an asphalt pavement structure, such as Figure 4 As shown, it includes a base layer 2 and a surface layer 1. A drainage layer is embedded in the surface layer 1. The drainage layer is formed by laying several parallel hemp ropes 100. The ends of the hemp ropes 100 extend to The side slope of the road shoulder to allow the asphalt surface to seep out of the road surface.
[0040] Specifically, the surface layer 1 is provided with several grooves 101 distributed in parallel, and the extending direction of the grooves 101 is set at an angle to the extending direction of the road surface. In this embodiment, the extending direction of the grooves 101 is set The included angle with the center line of the road surface is 60°, the depth of the groove body 101 is 10-12 cm, and the width is 0.4-0.6 cm, but it is not limited thereto.
[0041] In order to make the seepage of the surface layer 1 can be effectively discharged to the shoulder, the end of the...
Embodiment 3
[0045] This embodiment provides an asphalt pavement structure, such as Figure 5 As shown, the difference between embodiment 3 and embodiment 2 is that the angle between the extension direction of the groove body 101 and the centerline of the road surface is 30°.