A construction method and the technology of the outer leaf wall, which are applied in the direction of buildings, building components, building structures, etc., can solve the problems of reducing the energy saving effect of the wall, slow construction speed, and poor construction conditions of the outer leaf wall, so as to improve the energy saving effect , improve the assembly rate, improve the effect of force performance
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
specific Embodiment approach 1
[0050] Specific implementation mode one: see Figure 1-Figure 13 This embodiment will be described. The construction method of the assembled outer leaf wall of the sandwich wall of the cluster building described in this embodiment specifically includes the following steps:
[0051] (1) When constructing the main wall structure anchored by the outer leaf wall, the support member supporting the outer leaf wall is pre-embedded in the lower part of the main wall structure, and the anchor piece 9 of the tie-drawing device is pre-embedded in the upper part,
[0052] (2) On the bottom joist 2 of the outer leaf wall 1, the bottom support embedded parts and the prestressed tendon anchor embedded parts 3 of the outer leaf wall are arranged, and the bottom support embedded parts are used to pre-embed and support the outer leaf wall with the lower part of the main wall structure The supporting parts cooperate with the anchor connection;
[0053] (3) Build the outer leaf wall 1 above the...