Construction method for replacing middle rock pillar in high ground stress soft rock with large deformation and ultra-small clear distance tunnel
A technology of high ground stress and construction method, applied in tunnels, tunnel linings, earthwork drilling, etc., can solve the problems of tunnel collapse and self-stabilization, achieve good mechanical performance, ensure safety and stability, and operate conveniently and quickly Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0034] like figure 1 , Image 6 As shown, this embodiment provides a medium rock pillar structure 4 for replacement of a tunnel in high ground stress soft rock with large deformation and ultra-small clear distance, including prestressed connectors, concrete 42 and fasteners 43 .
[0035] The ultra-small clear distance tunnel includes the long-span section 1 of the combined tunnel repair and the sub-repair tunnel 2, and the replacement middle rock pillar structure 4 is fixedly arranged in the sub-repair tunnel 2.
[0036] The number of prestressed connectors is several, specifically, the prestressed connectors are prestressed steel pipes 41; the prestressed steel pipes 41 have high strength and good force bearing capacity, which can improve the safety and stability of the rock pillar structure 4 in the replacement, Several prestressed steel pipes 41 are vertically arranged in a row in contact with each other. Prestressing can apply pressure to the connector in advance before ...