A construction method and foundation pit technology, which is applied in infrastructure engineering, excavation, construction, etc., can solve the problems of groundwater infiltration into foundation pits, surface settlement, water level drop, etc., and achieve stability, good seepage resistance, and good stability Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0038] The present invention will be described in further detail below in conjunction with the accompanying drawings.
[0039] A construction method of an anti-seepage system after a foundation pit disclosed by the present invention comprises the following steps:
[0040] S1. The foundation pit has been supported by piles and anchors, and excavated to the bottom of the foundation pit.
[0041] S2, refer to figure 1 , on the side of the foundation pit facing the river and between the adjacent slope protection piles 1, the high-pressure jet spraying forms the jet jetting pile 2 that engages with the slope protection pile 1, and the jet jetting pile 2 and the slope protection pile 1 combine to form a curtain, and the bottom surface of the jet jetting pile 2 The elevation is the same as the elevation of the bottom surface of the slope protection pile 1, and the elevation of the top surface of the jet grouting pile 2 is higher than the highest water level of the groundwater, prefe...
Embodiment 2
[0050] refer to Figure 4 , the difference from Embodiment 1 is that in step S3, the gap between the slope protection pile 1, the jet grouting pile 2 and the anti-seepage wall 3 near the river channel is sealed. When making the guide wall 4 of the anti-seepage wall 3, the horizontal part 41 of the guide wall 4 close to the slope protection pile 1 is engaged with the slope protection pile 1 and the rotary grouting pile 2, and the thickness of the horizontal part 41 is thickened at the same time. The thickness of 41 is at least 1m, and the steel skeleton is set in the horizontal part 41 of the guide wall 4, and the position where the slope protection pile 1 and the rotary grouting pile 2 are engaged with the horizontal part 41 is chiseled, and then the template of the guide wall 4 is erected to conduct the guide wall. Pouring of wall 4. After the pouring of the guide wall 4 is completed and the formwork is removed, the construction of the anti-seepage wall 3 is carried out. Bet...