A construction method and an overall improvement technology, applied in construction, building maintenance, building construction, etc., can solve the problems of damage to the internal structure of the building, time-consuming and expensive, and achieve a small safety risk, reduce the difficulty of demolition, and solve safety problems. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0049] to combine Figure 1 to Figure 10 As shown, the construction method for the overall upgrading and replacement of new and old steel roofs provided in this embodiment includes the following steps:
[0050] Step one, such as figure 1 As shown, an assembled tire frame 3 is set directly under the old steel roof 1 that needs to be removed, and the new steel roof 4 is integrally assembled on the assembled tire frame 3; after the overall assembly of the new steel roof 4 is completed, the new steel roof 4 and lay isolation protection device 6 on it.
[0051] For large-space steel structure buildings, the old steel roof 1 provides support through the peripheral permanent structure 2 of the building, and the peripheral permanent structure 2 can be a structural column. The old steel roof 1 has the characteristics of large span and heavy weight.
[0052] In the overall assembly of the new steel roof 4, a crane 5 is used for auxiliary construction. The orthographic projection area...
Embodiment 2
[0080] The difference between this embodiment and the first embodiment is that the construction sequence of step 6 to step 8 in the first embodiment is adjusted. The specific adjustments are:
[0081] Step 6. Cut and disassemble the old steel roof on the operating platform provided by the new steel roof, and use a crane to remove the cut old steel roof components to complete the demolition work of the old steel roof;
[0082] Step 7. Remove the temporary fixation around the new steel roof, and the computer control system controls the lifting power mechanism to lift the new steel roof to the design level;
[0083] Step 8: Complete the fixed connection between the new steel roof and the peripheral permanent structure.
[0084] It can be seen that step 6 of this embodiment is based on step 5, first remove the old steel roof on the new steel roof, and then raise the new steel roof to the design elevation separately, and realize the new steel roof The roof is fixed.