Project plan permission control method based on classification
What is Al technical title?
Al technical title is built by PatSnap Al team. It summarizes the technical point description of the patent document.
A technology of project planning and permission control, applied in the field of project management, it can solve the problems that scenarios cannot be realized, user roles cannot be edited, and special application scenarios cannot be satisfied, and the effect of meeting application requirements can be achieved.
Active Publication Date: 2021-03-09
CHENGDU AIRCRAFT DESIGN INST OF AVIATION IND CORP OF CHINA
View PDF6 Cites 0 Cited by
Summary
Abstract
Description
Claims
Application Information
AI Technical Summary
This helps you quickly interpret patents by identifying the three key elements:
Problems solved by technology
Method used
Benefits of technology
Problems solved by technology
However, in practice, it is also found that this method has defects and cannot meet the needs of special application scenarios, such as figure 1 As shown in , the user role of the first-level organization needs to control the first four levels of WBS, so that it cannot be edited by the user roles of the second-level organization and the third-level organization
If the conventional organization-based access control method is adopted, the above scenarios cannot be realized
Method used
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more
Image
Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
Click on the blue label to locate the original text in one second.
Reading with bidirectional positioning of images and text.
Smart Image
Examples
Experimental program
Comparison scheme
Effect test
Embodiment 1
[0032] In this embodiment, combined with figure 2 with image 3 , providing a category-based method for project plan authority control, the method comprising the following steps:
[0033] Step 1: Set up a classification dictionary in the project management system according to the hierarchy and authority control requirements of the enterprise organization.
[0034] Assuming that the hierarchy of the enterprise organization is divided into N layers, the classification dictionary of the project plan tree includes N classification plans; the first type of plan corresponds to the plan created by the user role of the first-level organization, and the second type of plan corresponds to the user role of the second-level organization Created plans, and so on, the Nth type of plan corresponds to the plan created by the N-level organization user role. In this embodiment, the hierarchy of the enterprise organization is divided into three layers, and the classification dictionary includ...
Embodiment 2
[0051] Specifically, taking an enterprise as an example, combining Figure 4 with Figure 5 , the category-based project planning control permission method includes the following steps:
[0052]Step 1: The organizational structure related to project management of the enterprise is divided into three layers, namely:
[0053] The project management office (a first-level institution), whose user role is the project supervisor;
[0054] The research department (secondary organization), whose user role is the research department planner;
[0055] Research room (three-level organization), whose user role is the research room planner.
[0056] Corresponding to these three-tier organizations, set up a classification dictionary for project plans, including three categories:
[0057] A type of plan (corresponding to the plan created by the project director of the project management office of the first-level institution);
[0058] Type II plan (corresponding to the plan created by t...
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More
PUM
Login to View More
Abstract
The invention belongs to the field of project management, and relates to a project plan permission control method based on classification, which specifically comprises the following steps: setting a classification dictionary in a project managementsystem according to the hierarchy and permission control requirements of an enterprise organization; setting a'plan category 'attribute on a WBS objectof a project plan tree in the project managementsystem; designing an authority control rule of the project plan tree based on the category attribute of the WBS object; after the user of each layer of institution completes the compilation of the WBS in the project management system, the institution level to which the user belongs is created according to the WBS, and the project management systemautomatically sets the category attribute value of the WBS based on the classification dictionary; and the project management system gives different editing authorities to the project plan tree to theuser based on the'plan category 'attribute value of the WBS on the project plan tree by judging the organization level to which the user role belongs. Project planningauthority control requirementsin actual service can be met, and the planning authority control capability of the project management system is improved.
Description
technical field [0001] The invention belongs to the field of project management, and in particular relates to a classification-based project plan authority control method. Background technique [0002] In the existing project management system, the project plan tree is mainly reflected in WBS (Work Breakdown Structure, work breakdown structure), such as figure 1 shown. [0003] WBS is a multi-layer tree structure. Each WBS node has typical attributes such as name, planned start time, planned completion time, and organizational structure (such as figure 1 ). At present, when constructing the authority control mechanism of the project plan and designing the authority of each type of role in the project management system for editing the project plan tree, the scope of authority is usually defined based on the organization to which the WBS belongs. For example, the user role of the first-level organization has the editing authority of the WBS of the first-level organization a...
Claims
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More
Application Information
Patent Timeline
Application Date:The date an application was filed.
Publication Date:The date a patent or application was officially published.
First Publication Date:The earliest publication date of a patent with the same application number.
Issue Date:Publication date of the patent grant document.
PCT Entry Date:The Entry date of PCT National Phase.
Estimated Expiry Date:The statutory expiry date of a patent right according to the Patent Law, and it is the longest term of protection that the patent right can achieve without the termination of the patent right due to other reasons(Term extension factor has been taken into account ).
Invalid Date:Actual expiry date is based on effective date or publication date of legal transaction data of invalid patent.
Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q10/10G06K9/62
CPCG06Q10/103G06F18/28G06F18/241
Inventor 周四磊许媛媛何俊林冯大川黎志碧李嘉骏
Owner CHENGDU AIRCRAFT DESIGN INST OF AVIATION IND CORP OF CHINA