A construction method, the technology of riding a well, is applied in the sewer pipeline system, waterway system, building, etc. It can solve the problems of narrow construction space, inability to weld, and affect welding quality, so as to achieve convenient angle adjustment, ensure the quality of pouring, and solve the problem of branch demolition difficult effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0050] In the following, the present invention will be more clearly and completely described by way of embodiments in conjunction with the accompanying drawings, but the present invention is not limited to the scope of the described embodiments.
[0051] like Figure 1 to Figure 7 As shown, the present embodiment provides a construction method for pipe jacking riding wells, which includes the following steps:
[0052] S1. Excavate the pipe jacking joint 4 provided with the outer steel plate 5 and expose the pipe jacking joint 4 to the outside, and measure and verify the basic information such as the size and positioning of the outer steel plate 5;
[0053] S2. Hoist the steel cylinder into the foundation pit, and align it with the outsourcing steel plate 5 on the pipe jacking joint 4, and connect the steel cylinder and the outsourcing steel plate 5;
[0054] S3, pouring concrete in the steel cylinder;
[0055] S4. Build a brick well shaft and a complete set of anti-settling ...