[0057] Such as figure 1 with figure 2 As shown, a bracket preloading mechanism, brackets 2 are arranged on both sides of the upper end of the pier body 1, and the first distribution beam 21 and the second distribution beam 21 are respectively laid on the brackets 2 on both sides of the pier body 1 along the length direction of the pier body. Two distribution beams 22, the first distribution beam 21 and the second distribution beam 22 are double-beam I-beam distribution beams. It includes two preloading units arranged at intervals along the length direction of the pier body 1, wherein the length direction of the pier body is figure 2 In the direction indicated by the arrow A. The pre-compression unit is located above the bracket 2 .
[0058] Such as figure 1 As shown, the preloading unit includes a jack 3, a first reaction force frame 5, a second reaction force frame 6, a first support column 6 and a second support column 7; wherein, the first reaction force frame 5 and ...
Embodiment 2
[0065] A method for bracket preloading using the bracket preloading mechanism in Embodiment 1, comprising the following steps:
[0066] Step 1. On the brackets 2 on both sides of the pier body 1, the first distribution beam 21 and the second distribution beam 22 are respectively laid along the length direction of the pier body, and the at least two preloading units arranged at intervals along the length direction of the pier body are determined. position, install the pre-compression unit, the pre-compression unit is mainly installed by the following methods: step S1, respectively install the first support column 6 and the second support column 7 on the top of the pier body 1; step S2, the second support column installed in step S1 A support column 6 is installed with the first reaction force frame 5, and then the second support column 7 installed in step S1 is installed with the second reaction force frame 6, after that, connect one end of the first reaction force frame 5 with ...