Sponge city road structure and construction method
A road structure and sponge city technology, applied in infrastructure engineering, roads, roads, etc., can solve the problems of water seepage, water storage, water purification, stagnant water, etc., and achieve the goal of expanding space, strong integrity, and stable structure Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0028] The sponge city road structure includes permeable sidewalks 1, lateral permeable curbs 2, inspection openings 3, ground permeable roadways 4, central green belts 5, impermeable side walls 6, leveling fine sand layers 7, geotechnical Fabric 8, graded filter layer 9, permeable opening 10, vertical water pipe 11, inverted arch 12, pile 13, impermeable top layer 14, impermeable side wall 15, impervious floor 16, underground impermeable driveway 17, underground waterway 18. Underground comprehensive pipe gallery 19, planting soil 20 and communication channel 21; the bottom of the sponge city road structure is provided with piles 13 and inverted arches 12, and the top of the piles 13 and inverted arches 12 is provided with an impervious floor 16, The two ends of the inverted arch 12 are provided with impermeable side walls 6, and the middle part between the inverted arch 12 and the impermeable floor 16 is provided with an underground integrated pipe gallery 19, and the two sid...
Embodiment 2
[0033] The construction method of described sponge city road structure, comprises the following steps:
[0034] 1) if figure 2 As shown, the road foundation pit is excavated, and the reinforced concrete prefabricated piles are laid to the design depth according to the design requirements, then the steel bars of the inverted arch 12 are bound, the formwork is set up and the concrete is poured to form the inverted arch 12, and then the steel bars reserved in the middle of the inverted arch 12 Bind the steel bars of the side walls of the underground comprehensive pipe gallery 19, pour concrete to form them, and finally bind the steel bars of the impermeable floor 16 on the top of the underground comprehensive pipe gallery 19 and the pile 13, and reserve the permeable openings 10 and vertical water pipes 11 at the corresponding positions After the channel and the inspection port 3, the concrete is poured;
[0035] 2) if image 3As shown, the impermeable side walls 6 are poured ...