Anti-cracking waterproof structure at joint of decorative moulding and wall body and construction process
A decorative line, waterproof structure technology, applied in building structure, construction and other directions, can solve the problems of wall leakage, cracking, falling off, etc., to avoid costs, avoid maintenance costs, and easy to operate.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0020] The present invention is an anti-cracking and waterproof structure at the joint between the decorative molding and the wall, comprising an outer wall 6 and a finished decorative molding 5 arranged on the outside of the outer wall 6, and the connection between the upper inner corner of the finished decorative molding 5 and the outer wall 6 An anti-cracking and waterproof structure is provided at the place, and the anti-cracking and waterproof structure includes a rounded corner 4 provided with mortar at the connection between the upper inner corner of the finished decorative line 5 and the outer wall 6; the outer side of the rounded corner 4 is provided with a paint Waterproof layer 3 ; the outer side of the paint waterproof layer 3 is provided with an alkali-resistant mesh cloth 2 , and the outer side of the alkali-resistant mesh cloth 2 is provided with an exterior wall plaster layer 1 .
[0021] In this embodiment, the rounded corner 4 is a 45° rounded corner.
[0022...
Embodiment 2
[0025] A construction process of the anti-cracking waterproof structure at the joint between the decorative line and the wall of the present invention comprises the following steps:
[0026] Step 1. Pop up the control line at the elevation of the finished decorative line 5 on the outside of the outer wall 6, reserve the installation position of the finished decorative line 5, and reserve a 300mm outer wall plaster layer 1 at the installation position of the finished decorative line 5 s position;
[0027] Step 2: When the upper external wall painting layer 1 is painted to the position where the finished decorative line 5 is to be installed, install the finished decorative line 5, and align the vertical and horizontal gaps of the finished decorative line 5 with the ink line to keep the width of the gap consistent. Line 5 must be installed horizontally and vertically, within the allowable tolerance range, to ensure that the finished decorative line 5 is free from damage, missing ...