A technology of water jet and integrated machine, which is applied in the direction of drilling equipment and methods, cutting machinery, and installation of bolts, etc. It can solve the problems of complex anchorage rock formation structure, high stress in the deep part of the roadway, and low driving efficiency, so as to achieve multi-path Support, improve tunneling efficiency, and reduce the effect of roadway space deformation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] see Figure 1-Figure 5 , an integrated bolter digging machine integrated with a water jet system, specifically applied to coal excavation, includes an integrated bolter digging machine 1 and a water jet system arranged on the integrated bolter digging machine 1, and the integrated bolter digging machine 1 includes For the cutting drum 9 for construction on the face, the water jet system includes a water jet drilling device and a face cutting device both arranged on the integrated bolter 1, and the face cutting device is used for The water jet drilling device is used for drilling or drilling and slitting operations for performing slitting operations on the face of the face.
[0041] The face cutting device includes a water jet nozzle 13 and a nozzle multi-degree-of-freedom boom 14, the water jet nozzle 13 is arranged on the nozzle multi-degree-of-freedom boom 14, and the nozzle multi-degree-of-freedom boom 14 is arranged on On the integrated bolter 1. The palm face sli...
Embodiment 2
[0065] see Image 6 The difference between this embodiment and Embodiment 1 is that the water jet drilling device is different. The water jet drilling device in this embodiment includes a water jet drilling rod 16 and a drilling machine, and the water jet drilling rod 16 is detachably arranged on the On the drilling rig, a water jet drill pipe storage is provided on one side of the drilling rig, and water jet drilling rods of different specifications are arranged in the water jet drilling rod storage. Among them, the drilling rig comes with the bolter. By replacing the original drill pipe with a water jet drill pipe, drilling or drilling and cutting operations can also be realized. The end of the water jet drill pipe is connected to the high-pressure hose through a rotary joint. to achieve normal work. According to the existing structure of the bolter miner, the drilling rig is arranged on the cutting boom 8 through the sliding platform and the rotary platform. The advantage ...