Tunnel foamed aluminum plate and secondary lining concrete integral pouring construction method
A foamed aluminum plate and construction method technology, which is applied in the direction of tunnel lining, tunnel, earthwork drilling, etc., can solve the problems of lack of construction method research, etc., and achieve the effect of saving the process of installing foamed aluminum plate, improving operation efficiency, and simple construction operation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0032] see Figure 1-Figure 3 , a tunnel construction method of foamed aluminum plate and secondary lining concrete, the method involves the use of a special connector.
[0033] The connector includes a first member 4 and a second member 5, the first member 4 is a cylinder, a threaded hole 6 is provided inside the first member 4 and a raised texture is provided on the outer surface, the first member 4 The second member 5 is a panel structure, the first member 4 is vertically arranged on the second member 5 , and the second member 5 is provided with a first through hole 8 and a second through hole 9 corresponding to the threaded hole 6 .
[0034] Described construction method comprises the following steps:
[0035] Step S1: Attach one side of the aluminum foam board 2 to the side of the second member 4 away from the first member 5, and connect the aluminum foam board 2 to the connector through the cooperation of the screw 11 and the first through hole 8;
[0036] Step S2: Lay...