Embodiment 1
[0034] Embodiment one: 1) preparatory work requires excavation and transport tools commonly used such as: hoist, excavator and transporter etc.;
[0035] 2) Select the excavation position, dig a pothole of suitable size, then lay the gasket 4 on the outside of the pit, and the depth of the pit is 40 cm;
[0036] 3) Use a hoist to stabilize the stabilization ring 1, and the device can sink stably through the weight of the stabilization ring 1 and the stake 2 itself. When it sinks to the designated position, it can be connected to the extension ring 5 on the top, and the sinking height is 5 cm ;
[0037] 4) Lay a water expansion ring on the top of the stabilization ring 1, apply lubricating oil to the outside of the expansion ring, place the extension ring 5 and the stabilization ring 1 horizontally, and then fix the extension ring 5 with the protection ring 6 after placing it stably to ensure that the extension ring 5 stability;
[0038] 5) If the length of the cylinder compo...
Embodiment 2
[0041] Embodiment two: 1) preparatory work requires excavation and transport tools commonly used such as: hoist, excavator and transporter etc.;
[0042] 2) Select the excavation position, dig a pothole of suitable size, then lay the gasket 4 on the outside of the pit, and the depth of the pit is 50 cm;
[0043] 3) Use a hoist to stabilize the stabilization ring 1. The device can sink stably through the weight of the stabilization ring 1 and the stake 2 itself. When it sinks to the designated position, it can be connected to the extension ring 5 on the top. The sinking height is 15 cm ;
[0044] 4) Lay a water expansion ring on the top of the stabilization ring 1, apply lubricating oil to the outside of the expansion ring, place the extension ring 5 and the stabilization ring 1 horizontally, and then fix the extension ring 5 with the protection ring 6 after placing it stably to ensure that the extension ring 5 stability;
[0045] 5) If the length of the cylinder composed of ...
Embodiment 3
[0048] Embodiment three: 1) pre-preparation work requires commonly used excavation and transport tools such as: hoist, excavator and transporter etc.;
[0049] 2) Select the excavation position, dig a pothole of suitable size, then lay the gasket 4 on the outside of the pit, and the depth of the pit is 60 cm;
[0050] 3) Use a hoist to stabilize the stabilization ring 1, and the device can sink stably through the weight of the stabilization ring 1 and the stake 2 itself. When it sinks to the designated position, it can be connected to the extension ring 5 on the top, and the sinking height is 30 cm ;
[0051] 4) Lay a water expansion ring on the top of the stabilization ring 1, apply lubricating oil to the outside of the expansion ring, place the extension ring 5 and the stabilization ring 1 horizontally, and then fix the extension ring 5 with the protection ring 6 after placing it stably to ensure that the extension ring 5 stability;
[0052] 5) If the length of the cylinde...