[0013] A kind of gypsum block filling wall construction pouring method described in the present embodiment comprises the following steps:
[0014] Install a special formwork on the 100mm thick wall, fill the foam board in the middle, and 25mm gap between the foam board and the formwork; pre-embed the water and electricity pipeline; mechanically stir the raw materials such as gypsum, water and retarder into gypsum slurry according to a certain proportion, The ratio is: the mass ratio of gypsum, water and retarder is 100:60:1; the prepared gypsum slurry is poured into the mold through the gypsum slurry pouring machine, and vibrated; after 30 minutes, the wall after demoulding Construction completed.
Embodiment 2
[0016] A kind of gypsum block filling wall construction pouring method described in the present embodiment comprises the following steps:
[0017] Install a special formwork on the 100mm thick wall and pour it into a solid body; pre-embed the water and electricity pipeline; mechanically stir raw materials such as gypsum, water and retarder into gypsum slurry according to a certain proportion, and the ratio is: gypsum, water and retarder The mass ratio is 100:80:1; the prepared gypsum slurry is poured into the mold through the gypsum slurry pouring machine, and vibrated; after 30 minutes, the wall construction is completed after demoulding.
Embodiment 3
[0019] A kind of gypsum block filling wall construction pouring method described in the present embodiment comprises the following steps:
[0020] Install a special formwork on the 100mm thick wall, and pour it into a circular hollow body in the middle; pre-embed the water and electricity pipeline; mechanically stir the raw materials such as gypsum, water and retarder into a gypsum slurry according to a certain proportion, and the ratio is: gypsum, water The mass ratio with the retarder is 100:68:1; the prepared gypsum slurry is poured into the mold through the gypsum slurry pouring machine, and vibrated; after 30 minutes, the wall construction is completed after demoulding.
[0021] The method of the invention reduces the intermediate link of production in the gypsum block factory, utilizes the natural drying of the wall body, and the product can be completely dried within 15 days in winter, which solves the drying and drying links of the production in the factory, and elimina...