Drilling simulation experiment device
A technology for simulating experimental equipment and drilling, which is used in material inspection products, soil material testing, etc., and can solve problems such as the inability to measure rock drillability.
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2011-12-21
- Estimated Expiration
- Not applicable · inactive patent
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention relates to a simulation experiment device for parameters related to drilling in an oil field, in particular to a drilling simulation experiment device that provides reliable theoretical data for near-balanced, under-balanced, and over-balanced drilling in an oil field, so as to formulate a more reasonable drilling implementation plan. Background technique
[0002] With the development of drilling technology, near-balanced, under-balanced and over-balanced drilling technologies are all applied, among which under-balanced drilling technology has been proved to be a feasible and cost-effective method. In conventional overbalanced or near-balanced drilling, in addition to carrying cuttings, stabilizing the well wall, and cooling the drill bit, the drilling fluid is more important to balance the formation pressure and prevent the formation fluid from entering the wellbore. In underbalanced drilling, the bottom hole circulation pressure is cons...
Examples
Embodiment Construction
[0018] In order to have a clearer understanding of the technical features, purposes and effects of the present invention, the specific implementation manners of the present invention will now be described with reference to the accompanying drawings.
[0019] Such as figure 1 , figure 2 , image 3 As shown, the present invention proposes a drilling simulation experiment device 100. The simulation experiment device 100 includes a core clamping mechanism 1 and a drilling mechanism 2 installed coaxially on the upper and lower sides. The core clamping mechanism 1 is connected with a first implement. Pressure mechanism 3, the upper and lower ends of the core clamping mechanism 1 are respectively connected with the first pressure application control pipeline 4 and the second pressure application control pipeline 5, and the drilling mechanism 2 is connected with the second pressure application mechanism 6; as figure 1 , figure 2 As shown, the core clamping mechanism 1 includes a ...