Pier and horizontal tie beam bracket support synchronization construction method

A technology of synchronous construction and construction method, which is applied in the direction of bridges, bridge construction, erection/assembly of bridges, etc., and can solve the problem of inability to achieve synchronous, fast and simple construction of pier columns and transverse beams, and the inability to realize transverse beams and pier columns Simultaneous construction, cumbersome construction procedures, etc., to achieve the effect of less materials used, low construction cost, and high turnover utilization rate
CN103866697AActive Publication Date: 2014-06-18CHINA RAILWAY ERJU 1ST ENG +1

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
CHINA RAILWAY ERJU 1ST ENG
Publication Date
2014-06-18

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
  • Figure 3
    Figure 3
Patent Text Reader

Abstract

The invention discloses a pier and horizontal tie beam bracket support synchronization construction method. A novel bracket support method is used, a bracket is welded to a pier column model, after the pier column model is arranged, a support platform for tie beam construction is arranged on the bracket, and then the following procedures of a tie beam bottom die, a top plate steel rib, a tie beam side die, a pier column, horizontal tie beam concrete and the like are carried out. According to the construction method, synchronization construction of the pier column and a horizontal tie beam is achieved, the construction cycle of parts (the pier column, the horizontal tie beam and the like) below a bridge is shortened, the bridge construction progress is accelerated, the technology is safe and controllable, meanwhile, compared with a traditional construction scheme, operation is easy, and investment cost is low.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention relates to a method for synchronous construction of bridge piers and transverse tie beams, in particular to a method for using a novel corbel bracket platform for simultaneous construction of bridge piers and transverse tie beams. Background technique

[0002] When designing high bridge piers, it is necessary to set transverse beams between the two pier columns to increase the lateral stiffness of the pier body and prevent the lateral instability of the pier body. The traditional methods for erecting the construction platform of high pier transverse tie beams include bracket method, steel rod method and hoop method.

[0003] The steel bar method and the hoop method need to complete the construction of the pier column first, and then install the tie beam construction platform on the pier column after piercing the steel bar or installing the hoop, and then construct the tie beam, that is, the pier column and the transverse tie beam are sepa...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine