Construction layout of underground nuclear power station combination grotto group along depth direction of mountain body
A technology for cavern groups and nuclear power plants, which is applied in the fields of detailed information of nuclear power plants, nuclear engineering, nuclear power generation, etc., can solve the problems of high modularization requirements, high hollowing rate of mountain bodies, and increased investment, so as to meet the overall requirements and modularization. The effect of high degree and few construction passages
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0020] The present invention will be described in further detail below in conjunction with the accompanying drawings and embodiments, but these embodiments should not be construed as limiting the present invention.
[0021] see Figure 1 to Figure 3 , the present invention's underground nuclear power plant combined cavern group construction layout along the depth direction of the mountain body, including nuclear reactor powerhouse cavern 1, combined cavern, electrical powerhouse cavern 2, pressure relief cavern 7, first main traffic tunnel 8, second main tunnel Traffic tunnel 9, third main traffic tunnel 10, top-level branch tunnel system, bottom-floor branch tunnel system, main steam channel 11, equipment channel 12, branch traffic tunnel 13 and side traffic tunnel 14.
[0022] There are two nuclear reactor building caverns 1, and the line connecting the central axes of the two nuclear reactor building caverns 1 is perpendicular to the depth direction of the mountain body. O...