Construction method for empty hole through long spiral drilled press-grouting pile
A technology of long spiral drilling and construction method, applied in sheet pile wall, foundation structure engineering, construction and other directions, can solve the problems of prolonging the construction period, restricting the development of long spiral pile foundation, wasting time, etc., so as to improve the construction speed and efficiency. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0026] A construction method for empty holes of long auger bored grouting piles, as attached Figure 4 , 5 Shown, it is characterized in that comprising the following steps:
[0027] Step 1: Measure the pile position, use the special vibrator of pile driver 2 to clamp the casing, vibrate it to the bottom of the hole 50 cm, and then remove it;
[0028] Step 2: Once the pile driver is in place, after drilling to the predetermined depth of the pile hole, the pile hole will be drilled through the long auger drill rod.
[0029] Concrete is poured at the bottom, and at the same time, slowly lift the long auger until it reaches the bottom of the hole, stop the concrete, lift the long auger out of the pile hole, and move the pile driver away;
[0030] Step 3: Use the special vibrator of pile driver 2 to clamp the special guide rod, vibrate it to the lower part of the concrete surface 20 cm, open the cleaning device of the special guide rod, and then lift the special guide rod upward...