Integral one-time pouring construction method of large-volume concrete for special-shaped pier stud
A technology of mass concrete and construction method, applied in construction, erection/assembly of bridges, bridges, etc., can solve the problems of long construction period, increased density of steel bars, small operating space in the mold, etc., to ensure construction safety and save construction. cost, the effect of improving appearance quality and geometric dimensional accuracy
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0021] A construction method for integral one-time pouring of large-volume concrete for special-shaped pier columns, specifically comprising the following steps:
[0022] 1. Pre-embedded positioning of pier column reinforcement
[0023] After the steel bars on the top plate of the cap are installed, before the concrete construction, the measurement team will measure and set out the pier columns. Referring to the design dimensions of the cap: 1050cm long and 650cm wide, the vertical and horizontal axes of the pier columns will be released with a total station to determine the pre-planned dimensions of the pier column reinforcements. For the buried position, the on-site construction personnel used temporary steel bars to fix the position of the pier column based on the setting-out of the survey team, and prepared for the overall hoisting of the pier column steel bar. Use a crane to lift it into place at one time, and add temporary supports to ensure that the steel bars are not b...