A treatment method and technology of cast-in-situ piles, which are applied in underwater structures, infrastructure engineering, water conservancy projects, etc., can solve problems such as easy water leakage, large number of steel structures, and difficult external wall construction, and achieve the effect of enhancing reliability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0016] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0017] Such as Figure 1 to Figure 3 As shown, a connection processing method for the retaining cast-in-place pile in the reverse foundation pit and the basement structure floor, the specific steps are:
[0018] 1) Construction of the surrounding cast-in-place pile 1, excavation to the level of about 2m underground of the corresponding floor, the production of the surrounding beam 2, the way of inserting the H400 steel 4 into the surrounding beam 2 is to put the steel into the specified elevation when the steel bars are bound Location;
[0019] 2) For basement floor slab construction, the inner ring beam 3 is set at the first span of the outer wall of the structure 3, and the connection between the inner ring beam 3 and the waist beam 2 is connected with the H400 type steel 4 with the support plate belt 5; H400 The section steel 4 is located under the...